Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.

A. Bottom-up
...
... B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.

A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE

Total Views: 382Word Count: 329See All articles From Author

Add Comment

Education Articles

1. Time Management 101: Conquer Procrastination
Author: Patuck-Gala

2. Salesforce Devops Training? Streamlining Deployments With Salesforce Devops
Author: Eshwar

3. The Elzee Way Encouraging Curiosity In Toddlers Through Fun Exploration
Author: Elzee

4. Which School Give The Best Icse Kindergarten Experience In Bhopal?
Author: Adity Sharma

5. Data Scientist Vs Mlops Engineer
Author: Gajendra

6. Step-by-step Guide To Web Administrator 313113 Rpl Reports
Author: RPLforAustralia

7. Mba Distance Education
Author: Amrita singh

8. Best Cbse School In Tellapur
Author: Johnwick

9. Cypress Course Online | Cypress Training Course In Hyderabad
Author: krishna

10. Trusted Assignment Help Uk
Author: Masters Assignment Help

11. Mern Stack Training | Best Mern Stack Course
Author: Hari

12. A Complete Guide To Fulfilling Your Mbbs Dreams Abroad
Author: Mbbs Blog

13. Engaging Learning Techniques: Making Education Fun For Your Child
Author: Khushbu Rani

14. Playwright Course Online | Best Playwright Training
Author: Madhavi

15. The Best Gcp Data Engineer Certification Online Training | Hyderabad
Author: SIVA

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: