Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.

A. Bottom-up
...
... B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.

A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE

Total Views: 416Word Count: 329See All articles From Author

Add Comment

Education Articles

1. Guaranteed Grades: Pay Someone To Take My Exam
Author: Doug Macejkovic

2. Blocks Before Books
Author: Michale

3. Azure Devops Training Online | Azure Devops Online Training
Author: visualpath

4. Learn Python Programming - from Basics To advanced
Author: vishal more

5. Data Engineering Course In Hyderabad | Aws Data Analytics Training
Author: naveen

6. Oci Online Training | Oracle Cloud Infrastructure In Hyderabad
Author: visualpath

7. Best Salesforce Data Cloud Certification Training
Author: visualpath

8. The Benefits Of Online Dry Needling Certification
Author: Daulat

9. Top Google Cloud Data Engineer Training In Bangalore
Author: Visualpath

10. Aima’s Management Diploma: The Smart Choice For Future Leaders
Author: Aima Courses

11. How Regular Mock Test For Bank Help You Crack Bank Exams
Author: Ayush Sharma

12. Debunking The Myth: Is Preschool Just Playtime?⁠
Author: Kookaburra

13. Cps Global School: A World-class Learning Destination In Chennai
Author: CPS Global School

14. Chennai Public School: Shaping Future Leaders Through Excellence In Education
Author: Chennai Public School

15. "transform Your Data Analysis With Lcc Computer Education's Excel Training"
Author: Khushi Gill

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: