Question: 1

When considering risks, which describes an opportunity in a project?

A. An uncertain event that could have a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives

Answer: B

Question: 2

Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid,
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 3

Which may be funded from a risk budget?

A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of ...
... a fallback plan
D. Preparation of the Risk Management Strategy

Answer: C

Question: 4

What is the first task of product-based planning?

A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure

Answer: B

Question: 5

How many tasks does the product-based planning technique describe?

A. One
B. Two
C. Three
D. Four

Answer: D

Question: 6

Which is an objective of the quality review technique?

A. To identify a product's quality criteria
B. To provide assurance that the project is being conducted properly
C. To assess that a product conforms to set criteria
D. To ensure that staff are properly trained in the quality methods

Answer: C

Question: 7

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A. Risk category
B. Risk description
C. Risk response
D. Risk status

Answer: C

Question: 8

If an informal issue is defined as a problem or concern, where should it first be recorded?

A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report

Answer: C

Question: 9

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,

A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true

Answer: C

Question: 10

Which is the purpose of the Change theme?

A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty

Answer: B

Question: 11

Why is a Project Brief produced?

A. To act as a trigger for the Starting up a Project process
B. To record the strategies and management controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project

Answer: C

Question: 12

Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.

A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources

Answer: C

Total Views: 384Word Count: 606See All articles From Author

Add Comment

Education Articles

1. The Best Sap Ariba Training Course In Hyderabad | Sap Ariba Online Training
Author: krishna

2. Advance Your Career With A Level 3 Business Administration Qualification
Author: jann

3. List Of Top Online Ba University In India
Author: Studyjagat

4. Patient Manual Handling Course In Dublin: Essential Training For Healthcare Professionals
Author: johnymusks

5. Why Raj Vedanta Is The Best Icse School In Bhopal
Author: Ronit Sharma

6. Devops Training In Bangalore | Aws Devops Training Online
Author: visualpath

7. Unqork Online Training Institute | Unqork Training
Author: visualpath

8. Best Gcp Data Engineering Training | Google Cloud
Author: Visualpath

9. Salesforce Devops Course | Salesforce Devops Training
Author: himaram

10. How To Master Electrical And Mechanical Concepts For Rrb Alp Exam?
Author: Easy Quizzz

11. Generative Ai Courses Online | Genai Online Training
Author: Susheel

12. Oracle Cloud Infrastructure Online Training Institute | Visualpath
Author: visualpath

13. Aws Ai Certification | Ai With Aws Online Training India
Author: naveen

14. Why Do Students Struggle With Their Final Year Projects And How Can They Get Help?
Author: Paul J. Winters

15. Unlock Professional Growth With Leed Ap Certification
Author: Passyourcert

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: