Question: 1
Which of the following determines the account assignment category in sales order item? There are 2 correct answers to this question.
A. Requirement category
B. Requirement function
C. Requirements class
D. Requirements type
Answer: C,D
Question: 2
Which of the following levels can you assign persons to work centers? There are 2 correct answers to this question.
A. Capacity category level
B. Work center level
C. Workforce planning level
D. Assignment level
Answer: A,B
Question: 3
Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?
Please choose the correct answer.
A. Planned costing
B. Profitability costing
C. Overheads costing
D. Activity based costing
Answer: D
Question: 4
Which types of networks store all the activity and material component costs at the network
header level and behave ...
... in the same way as all other order categories?
Please choose the correct answer.
A. Order header networks
B. Assignment networks
C. Header assigned networks
D. Order category networks
Answer: C
Question: 5
Which of the following costs are automatically calculated based on the resource requirements
identified for activities and operations when using networks and activities?
Please choose the correct answer.
A. Manual costs
B. Actual costs
C. Planned costs
D. Element costs
Answer: C
Question: 6
Which of the following aids in calculating actual overheads based on the costing sheet and overhead key
entered?
There are 3 correct answers to this question.
A. Network header
B. Assignment
C. Network activity
D. WBS element
Answer: B,C,D
Question: 7
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?
Please choose the correct answer.
A. Budget transfer function
B. Budget release function
C. Budget Return function
D. Budget carry forward function
Answer: D
Question: 8
Which of the following can promptly identify commitments for a project that are too high and trigger
various actions in response?
Please choose the correct answer.
A. Tolerance limit
B. Availability control
C. Time horizon
D. Budget plan
Answer: B
yes, I am a Student and I am article author as well for CertsChief Network.
Add Comment
Education Articles
1. The Best Sap Ariba Training Course In Hyderabad | Sap Ariba Online TrainingAuthor: krishna
2. Advance Your Career With A Level 3 Business Administration Qualification
Author: jann
3. List Of Top Online Ba University In India
Author: Studyjagat
4. Patient Manual Handling Course In Dublin: Essential Training For Healthcare Professionals
Author: johnymusks
5. Why Raj Vedanta Is The Best Icse School In Bhopal
Author: Ronit Sharma
6. Devops Training In Bangalore | Aws Devops Training Online
Author: visualpath
7. Unqork Online Training Institute | Unqork Training
Author: visualpath
8. Best Gcp Data Engineering Training | Google Cloud
Author: Visualpath
9. Salesforce Devops Course | Salesforce Devops Training
Author: himaram
10. How To Master Electrical And Mechanical Concepts For Rrb Alp Exam?
Author: Easy Quizzz
11. Generative Ai Courses Online | Genai Online Training
Author: Susheel
12. Oracle Cloud Infrastructure Online Training Institute | Visualpath
Author: visualpath
13. Aws Ai Certification | Ai With Aws Online Training India
Author: naveen
14. Why Do Students Struggle With Their Final Year Projects And How Can They Get Help?
Author: Paul J. Winters
15. Unlock Professional Growth With Leed Ap Certification
Author: Passyourcert