Question: 1

What key benefits might stakeholders realize from an Agile approach?

A. The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily
B. The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments
C. Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting
D. The team’s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments

Answer: B

Question: 2

What is the first thing that a team should do to estimate user stories for a project?

A. Sort the user stories according to priority.
B. Schedule a team meeting to understand them.
C. Define the story points measure.
D. Estimate through function point analysis.

Answer: C ...
...

Question: 3

A story point is the:

A. Relative measure of the size of a user story.
B. Duration it takes to complete a user story.
C. Priority of the user story in the backlog.
D. Business value of the user story.

Answer: A

Question: 4

According to the Agile Manifesto, which of the following describes the more valued items?

A. Customer collaboration, following a plan, working software, and individual interactions
B. Working software, individual interactions, responding to change, and comprehensive documentation
C. Individual interactions, working software, customer collaboration, and responding to change
D. Responding to change, individual interactions, processes and tools, and customercollaboration

Answer: C

Question: 5

On a particular project, product quality is being measured at regular intervals and is consistently below the acceptable level. In a Lean environment, how should this problem be addressed?

A. The team should implement more rigorous testing at the end of each development cycle.
B. Management should direct the team on specific actions that they should take to improve quality.
C. Management should guide the team as it seeks to improve itself and reduce errors in the system.
D. The Project Champion should review the acceptable quality threshold to ensure that it is realistic.

Answer: C

Question: 6

In reference to Scrum, each sprint should produce:

A. An increment of potentially shippable product functionality.
B. Aset of documented product requirements and specifications.
C. Arelease with testable and measurable functionality.
D. An increment of potentially testable product functionality.

Answer: A

Question: 7

The primary purpose of a Sprint Review is for the team to:

A. Demonstrate what was accomplished during the sprint.
B. Discuss what went well, whatdidn’t, and ways to improve.
C. Prioritize and estimate stories planned for the next sprint.
D. Individually provide status updates on user stories in progress.

Answer: A

Question: 8

On what should Agile estimates be based?

A. A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan
B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes
C. Ball park figures collected from past Agile projects with scopes similar to the current project
D. Initial resource breakdown based on the available person days in the full project duration

Answer: B

Question: 9

A value stream map is a tool used to identify the:

A. Waste across the entire process.
B. Highest value product features.
C. Most valuable team interactions.
D. Most likely flow of project risks.

Answer: A

Question: 10

When estimating initial velocity, the team should most likely:

A. Discuss among the team their expectations of how many story points they can address.
B. Use a Kanban workflow to identify steps and calculate velocity.
C. Use velocity of past iterations or make a calculated guess.
D. Discuss with the customer their expectation for the velocity of producing the product.

Answer: C

Total Views: 584Word Count: 910See All articles From Author

Add Comment

Education Articles

1. Top It Skills To Learn In 2026 For A Successful Tech Career
Author: chandana bridgeon

2. Isaca Aaism Certification: Exam Cost, Requirements, Domains & Training Guide
Author: Passyourcert

3. Best Pre Primary School In Howrah: How Early Education Supports Your Child’s Development
Author: Siya

4. How Course Credits Affect Your High School Gpa
Author: Daniel Brooks

5. Singapore Student Visa Rejection 2026: Top Reasons & How To Avoid Them
Author: Nivesa EdTech

6. Ba Llb Coaching In Kolkata: A Complete Roadmap To Clat, Blat, Slat, Ailet & Mh Cet Success
Author: Amrita

7. Openshift Online Training | Openshift Training In Hyderabad
Author: Visualpath

8. Devops With Aws Course | Aws Devops Course In Hyderabad
Author: visualpath

9. Sap Ui5 Course | Sap Ui5 Fiori Training In Hyderabad
Author: naveen

10. Best Mlops Online Course | Mlops Training In India
Author: Vamsi Ulavapati

11. Does Your Bachelor’s Degree Decide Your Entire Career? Here’s The Truth
Author: UniversityGuru

12. Best Nda Foundation Course In Pune For Class 10 Students – Complete Guide
Author: Delhi Career Group

13. Cia Certification Course: Exam, Cost, Eligibility & Study Guide
Author: Passyourcert

14. Comptia A+ Certification: Complete Guide To Exam, Cost, Training & Career (2026)
Author: NYTCC

15. How Dms Research Can Help Professionals Address Real-world Organizational Challenges
Author: IIBMS

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: