Question: 1

What key benefits might stakeholders realize from an Agile approach?

A. The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily
B. The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments
C. Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting
D. The team’s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments

Answer: B

Question: 2

What is the first thing that a team should do to estimate user stories for a project?

A. Sort the user stories according to priority.
B. Schedule a team meeting to understand them.
C. Define the story points measure.
D. Estimate through function point analysis.

Answer: C ...
...

Question: 3

A story point is the:

A. Relative measure of the size of a user story.
B. Duration it takes to complete a user story.
C. Priority of the user story in the backlog.
D. Business value of the user story.

Answer: A

Question: 4

According to the Agile Manifesto, which of the following describes the more valued items?

A. Customer collaboration, following a plan, working software, and individual interactions
B. Working software, individual interactions, responding to change, and comprehensive documentation
C. Individual interactions, working software, customer collaboration, and responding to change
D. Responding to change, individual interactions, processes and tools, and customercollaboration

Answer: C

Question: 5

On a particular project, product quality is being measured at regular intervals and is consistently below the acceptable level. In a Lean environment, how should this problem be addressed?

A. The team should implement more rigorous testing at the end of each development cycle.
B. Management should direct the team on specific actions that they should take to improve quality.
C. Management should guide the team as it seeks to improve itself and reduce errors in the system.
D. The Project Champion should review the acceptable quality threshold to ensure that it is realistic.

Answer: C

Question: 6

In reference to Scrum, each sprint should produce:

A. An increment of potentially shippable product functionality.
B. Aset of documented product requirements and specifications.
C. Arelease with testable and measurable functionality.
D. An increment of potentially testable product functionality.

Answer: A

Question: 7

The primary purpose of a Sprint Review is for the team to:

A. Demonstrate what was accomplished during the sprint.
B. Discuss what went well, whatdidn’t, and ways to improve.
C. Prioritize and estimate stories planned for the next sprint.
D. Individually provide status updates on user stories in progress.

Answer: A

Question: 8

On what should Agile estimates be based?

A. A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan
B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes
C. Ball park figures collected from past Agile projects with scopes similar to the current project
D. Initial resource breakdown based on the available person days in the full project duration

Answer: B

Question: 9

A value stream map is a tool used to identify the:

A. Waste across the entire process.
B. Highest value product features.
C. Most valuable team interactions.
D. Most likely flow of project risks.

Answer: A

Question: 10

When estimating initial velocity, the team should most likely:

A. Discuss among the team their expectations of how many story points they can address.
B. Use a Kanban workflow to identify steps and calculate velocity.
C. Use velocity of past iterations or make a calculated guess.
D. Discuss with the customer their expectation for the velocity of producing the product.

Answer: C

Total Views: 595Word Count: 910See All articles From Author

Add Comment

Education Articles

1. Specialty Chemical Solutions Chennai: Supporting Diverse Industrial Applications
Author: Ivar

2. Best Chemical Supplier In Chennai: Supporting Diverse Industrial Requirements
Author: Ivar

3. Ssc Chsl Coaching In India: Complete Guide To Choosing The Right Coaching Institute
Author: Sreeli

4. A Beginner’s Guide To Choosing And Using Natural Crystals
Author: Narendra Sharma

5. Best Primary School In Howrah: Important Factors For Parents To Check
Author: Siya

6. Master Salesforce Devops Copado Ai Training | Visualpath
Author: Vamsi Ulavapati

7. Microsoft Fabric Training And Course Guide In Ameerpet
Author: Subahan

8. Best Agentic Ai Course Online Agentic Ai Training
Author: Hari

9. Pass Linux+ Certification: A Practical Study Plan For Xk0-006
Author: Passyourcert

10. Microsoft Copilot Studio Training | Agentic Ai Training
Author: Visualpath

11. Sap Ui5 Fiori Training | Sap Ui5 Fiori Training In Hyderabad
Author: naveen

12. Pgtrb Botany Online Coaching Tamil Nadu
Author: priyaa

13. Akashic Record Reading Course Online | Certification & Training
Author: Pushpa Viveka Healing Home

14. Cia Challenge Certification 2026: Eligibility, Exam Syllabus, Fees, Registration & Preparation Guide
Author: NYTCC

15. Cia Certification Guide 2026: Exam, Cost, Eligibility, Syllabus & Preparation
Author: passyourcert

Login To Account
Login Email:
Password:
Forgot Password?
New User?
Sign Up Newsletter
Email Address: