Question: 1
What key benefits might stakeholders realize from an Agile approach?
A. The ability to bypass the change-management process, inserting new requirements and changes directly into the team as they meet daily
B. The early and continuous delivery of valuable software, providing increased visibility and the opportunity for more frequent adjustments
C. Increased access to the project and less reliance on formal reports and status meetings to better understand the current work and the risks the team is accepting
D. The team’s flexibility to make changes mid-iteration as business needs or priorities change, increasing the ability of the team to meet project commitments
Answer: B
Question: 2
What is the first thing that a team should do to estimate user stories for a project?
A. Sort the user stories according to priority.
B. Schedule a team meeting to understand them.
C. Define the story points measure.
D. Estimate through function point analysis.
Answer: C ...
...
Question: 3
A story point is the:
A. Relative measure of the size of a user story.
B. Duration it takes to complete a user story.
C. Priority of the user story in the backlog.
D. Business value of the user story.
Answer: A
Question: 4
According to the Agile Manifesto, which of the following describes the more valued items?
A. Customer collaboration, following a plan, working software, and individual interactions
B. Working software, individual interactions, responding to change, and comprehensive documentation
C. Individual interactions, working software, customer collaboration, and responding to change
D. Responding to change, individual interactions, processes and tools, and customercollaboration
Answer: C
Question: 5
On a particular project, product quality is being measured at regular intervals and is consistently below the acceptable level. In a Lean environment, how should this problem be addressed?
A. The team should implement more rigorous testing at the end of each development cycle.
B. Management should direct the team on specific actions that they should take to improve quality.
C. Management should guide the team as it seeks to improve itself and reduce errors in the system.
D. The Project Champion should review the acceptable quality threshold to ensure that it is realistic.
Answer: C
Question: 6
In reference to Scrum, each sprint should produce:
A. An increment of potentially shippable product functionality.
B. Aset of documented product requirements and specifications.
C. Arelease with testable and measurable functionality.
D. An increment of potentially testable product functionality.
Answer: A
Question: 7
The primary purpose of a Sprint Review is for the team to:
A. Demonstrate what was accomplished during the sprint.
B. Discuss what went well, whatdidn’t, and ways to improve.
C. Prioritize and estimate stories planned for the next sprint.
D. Individually provide status updates on user stories in progress.
Answer: A
Question: 8
On what should Agile estimates be based?
A. A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan
B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes
C. Ball park figures collected from past Agile projects with scopes similar to the current project
D. Initial resource breakdown based on the available person days in the full project duration
Answer: B
Question: 9
A value stream map is a tool used to identify the:
A. Waste across the entire process.
B. Highest value product features.
C. Most valuable team interactions.
D. Most likely flow of project risks.
Answer: A
Question: 10
When estimating initial velocity, the team should most likely:
A. Discuss among the team their expectations of how many story points they can address.
B. Use a Kanban workflow to identify steps and calculate velocity.
C. Use velocity of past iterations or make a calculated guess.
D. Discuss with the customer their expectation for the velocity of producing the product.
Answer: C
Add Comment
Education Articles
1. How Mock Tests Help Students Prepare More Effectively For NeetAuthor: Sarthaks eConnect
2. How Indian Students Can Avoid Singapore Student Visa Rejection In 2026
Author: Nivesa EdTech
3. Ai Stack Course In Hyderabad | Ai Stack Training In Ameerpet
Author: Hari
4. The Celestial Rhythm: Understanding Mawaqit Al-salat (islamic Prayer Times)
Author: Sophia Eddi
5. The Rising Importance Of Data Science Skills In Ahmedabad’s Emerging It Landscape
Author: Arun
6. Ai Product Management | Ai Product Management Training Course
Author: Visualpath
7. Ai & Coding Training For Std 7 To 10 - Building Future Innovators With Smart Learning - Evision Technoserve
Author: Evision Technoserve
8. Proqual Level 7 Nvq: Elevate Your Safety Career Today
Author: Gulf Academy Safety
9. Join Sap Cpi Training In Hyderabad And Build Cpi Skills
Author: Pravin
10. Dryer Duct Booster Fan In Queens County: The Secret To Faster Drying And Better Home Safety
Author: cleanairrepair1
11. Synopsys To Hold Annual User Group Conference On June 18 In Bengaluru
Author: Madhulina
12. Best Areas In Pune For Students Learning Tech Courses 2026
Author: Fusionsoftwareinstitute
13. Pmi-pba Certification: The Ultimate Path To Becoming A High-impact Business Analysis Professional
Author: NYTCC
14. Capm Certification: Your First Step Toward A Successful Project Management Career
Author: Passyourcert
15. How To Start A Nursing Career From Scratch: A Complete Beginner's Guide
Author: Richard