An Organization's Duration Estimating Database
AN ORGANIZATION’S DURATION ESTIMATING DATABASE is the best reference information to use for estimating activity duration when activity durations are not driven by the actual work content. Organizations involved in the project may maintain duration estimating databases and other historical reference data that can be useful in estimating activity durations.
Assumptions and constraints from the project scope statement are considered when estimating activity duration schedules. PMP preparation reviews assumptions and constraints.
An example of an assumption is the length of the project reporting periods, which can dictate maximum scheduled activity duration.
An example of a constraint on schedule activity durations would be document submittals, reviews, and similar non-deliverable schedule activities, which have frequencies and durations either specified by contract, or within the performing organization's policies.
INEFFICIENCY caused by lack of adequate quantities or skills or materials, equipment, and labor/personnel, will significantly influence the duration of most activities. PMP prep courses ...
... include examples of inefficiencies.
THE RESOURCE CALENDAR developed as part of the activity resource estimating process includes:
Availability and capabilities skills of human resources
Availability and capability of equipment and material resources
THE RISK REGISTER has information on identified project risks. These risks must be considered when producing estimates of activity durations, or when activity durations for risks must be adjusted.
COMPLETED ACTIVITY COST ESTIMATES can be developed to provide estimated resource quantities for each schedule activity in the project activity list.
RESOURCE QUANTITY and PRODUCTIVITY RATE
THREE-POINT ESTIMATES are activity duration estimates that consider the amount of relative risk involved in the original estimate. Three-point estimates are based on estimates that might be:
The most likely
Optimistic (best-case scenario)
Pessimistic (worst-case scenario)
Using a combined average of the three types of estimates provides a more accurate activity duration estimate than a single-point estimate.
Project teams can choose to incorporate additional time into the project schedule.
These additions are referred to as:
Buffers
Contingencies
Reserves
Time Reserves (amounts of time added to the schedule to compensate for recognized schedule risk).
THE CONTINGENCY RESERVE may be a percentage of estimated activity duration, a fixed number of work periods, or may be developed by quantitative schedule risk analysis.
Develop the project schedule—Develop Schedule:
SCHEDULING is essentially the converting of the project action plan into a functioning timetable which provides the basis for monitoring and controlling the project.
Not all project activities need to be scheduled in the same level of detail.
Kimberly Bloch, To Get the proper PMP Exam Preparation training to pass the pmp exam certification exam with flying colors. Visit the site- pmeducate.com, too for some useful hints on Project Management PMP.
Add Comment
Education Articles
1. A Comprehensive Guide To Choosing The Right Sap Course For Your Career GoalsAuthor: lakshmana swamy
2. Ai Agent Course In Ameerpet | Training By Visualpath
Author: gollakalyan
3. Sap Ariba Online Training & Sap Ariba Course India
Author: krishna
4. Servicenow Cmdb Training | Servicenow Itom Course Online
Author: Hari
5. Redhat Openshift Training | Openshift Training In Hyderabad
Author: Visualpath
6. Industry-focused Data Science Course In Pune With Hands-on Learning
Author: Fusionsoftwareinstitute
7. Ai Llm Course | Llm Artificial Intelligence Course
Author: naveen
8. Fix The Green Gap: Isep Skills For Practical Managers
Author: Gulf Academy of Safety
9. Boost Learning With Easy & Effective Online Assessments
Author: Magicbox
10. School In Bangalore 2026-27 A Complete Guide To The Fees Ratings And Admissions
Author: shivam
11. Best Vapt Internship Program In India For Cybersecurity Students
Author: securium Academy
12. How Non-technical Professionals In Dehradun Are Entering The Data Science Industry
Author: dhanya
13. Explore Mbbs In Vietnam: Quality Education With Clinical Excellence
Author: Ashwini
14. Mbbs In Vietnam: Affordable Medical Education For Indian Students With Global Recognition
Author: Ashwini
15. Mbbs In Vietnam: World-class Medical Education At Reasonable Cost!
Author: ashwini