ALL >> Education >> View Article
Prince2-foundation Drill Kits

Question: 1
When considering risks, which describes an opportunity in a project?
A. An uncertain event that couldhave a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives
Answer: B
Question: 2
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Question: 3
Which may be funded from a risk budget?
A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. ...
... Implementation of a fallback plan
D. Preparation of the Risk Management Strategy
Answer: C
Question: 4
What is the first task of product-based planning?
A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure
Answer: B
Question: 5
How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Answer: D
Question: 6
Which is an objective of the quality review technique?
A. To identify a product's quality criteria
B. To provide assurance that the project is being conducted properly
C. To assess that a product conforms to set criteria
D. To ensure that staff are properly trained in the quality methods
Answer: C
Question: 7
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
A. Risk category
B. Risk description
C. Risk response
D. Risk status
Answer: C
Question: 8
If an informal issue is defined as a problem or concern, where should it first be recorded?
A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report
Answer: C
Question: 9
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Question: 10
Which is the purpose of the Change theme?
A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty
Answer: B
Question: 11
Why is a Project Brief produced?
A. To act as a trigger for the Starting up a Project process
B. To record the strategies andmanagement controls to be used by a project
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the Project Board as a basis for reviewing the progress of a project
Answer: C
Question: 12
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
A. the measurement of benefits NOT yet realized
B. the handover of products
C. open issues and risks
D. the release of resources
Answer: C
Question: 13
In what process is the authorization to deliver the project's products given?
A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Answer: D
Question: 14
Which of the following is NOT part of quality planning?
A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances
Answer: B
Question: 15
Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
Answer: A
Question: 16
Which is an objective of the Starting up a Project process?
A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled
Answer: A
Question: 17
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls
Answer: B
Question: 18
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier
Answer: C
Add Comment
Education Articles
1. Which Books Have Been Published By Iiag Jyotish Sansthan Founder Dr. Yagyadutt Sharma?Author: Yagya Dutt Sharma
2. Sap Sd Training In Bangalore
Author: VITSAP
3. Agile Scrum Methodology Explained In Simple Terms For Beginners
Author: Learnovative
4. Blue Wizard Liquid Drops 30 Ml 2 Bottles Price In Hyderabad
Author: bluewizard.pk
5. How Java Skills Can Open Doors To Global It Careers – Sssit Computer Education
Author: lakshmisssit
6. How Digital Marketing Can Help You Switch Careers
Author: madhuri
7. Ryan Group Of Institutions Partners With Royal Grammar School Guildford, A 500-year-old Institution - To Launch Premium British Curriculum Schools In
Author: Lochan Kaushik
8. Join Site Reliability Engineering Training Hyderabad | Visualpath
Author: krishna
9. Top 7 Tips From An Mbbs Admission Consultant In India
Author: Rima
10. An Ultimate Guide To Mbbs In Russia; An Ideal Destination To Study Mbbs Course!
Author: Mbbs Blog
11. A Complete Overview Of Mbbs In Nepal!
Author: Mbbs Blog
12. Affordable Online Mba’s With Global Recognition...
Author: University Guru
13. Induction Training: Building Strong Foundations For New Employees
Author: edForce
14. Dynamics 365 Training In Hyderabad | Online D365 Course
Author: Hari
15. Why Aima Leads In Post Graduate Diploma In Management Excellence
Author: Aima Courses